Scheduler Settings: Targets

An explanation of fields and properties

Scheduler Settings: Targets

To access this dialog:

  • In the Scheduler Settings dialog, select the Targets tab.

You can define one or more scheduling targets.

Field Details:

Primary objective: select the optimization objective; [Maximize NPV] or [Target tracking].

Ratios and Rates: click Add to add a new target, select a label and click Edit to modify an existing target, or select a label and click Delete to remove an existing target. Note that if a target is not selected, it will be inactive but still reported.

Pushback constraints: available in Multimine projects to apply pushback constraints to each of the mines. The Reset button will erase all entities in the table below.

Pushback table: this table contains the following columns:

  • Pushback: this column displays the index number of all available pushbacks.

  • Max Sink Rate: set the maximum number of benches each of the pushbacks can progress in a period.

  • Max Tonnage: set the maximum tonnage to be mined from a pushback in a period.

  • Start After: mining this pushback can start after the set period.

Edit Maximum Rock by Bench: allows you to set or edit the maximum mining rate per bench. Select a pushback and then set or edit the maximum mining rate.

Set to: will set the sink rate (if Set all rates is selected) or maximum tonnage (if Set all Tonnages is selected) mined for all pushbacks to the number provided. You can also define the sinking rate and maximum tonnage individually for each pushback using the Max Sink Rate and Max Tonnage columns.

You can also enter data directly into the table cells corresponding to a particular pushback for which limits are to be set.

 